Topics

Abrasive Blasting Case Studies GMA ToughBlast English Global

GMA ToughBlast™ saves 23 days in Water Tanks Maintenance Project

Overview

Project

Blasting of two water tanks

Location

Dayton, Ohio, USA

Task

Blast trial on two tanks during maintenance.

Challenge

Higher consumption, Lower productivity, achieved when using coal slag on Tank One.

A significant maintenance project involving two large multi-leg elevated water tanks, each with a capacity of two million gallons. The local painting contractor awarded the project used two different types of abrasive blasting products for each tank. Upon completion, the contractor found that one abrasive outperformed the other, resulting in a 22% total project cost saving.

Specifications

The tanks are supported by a central riser column and 12 peripheral legs. These structures are completely enclosed with tarps that can be adjusted for wind conditions. Access is provided via swing stages and catwalk platforms suspended between the columns. The tanks, which are 15 years old, have a total surface area of 6,782 m² (73,000 ft²) with a coating thickness of 25 to 30 mm. The internal surface area is 2,601 m² (28,000 ft²), while the external surface area is 4,181 m² (45,000 ft²).

Total project cost savings

7.7%

Savings

$26,576

Investment

Using GMA ToughBlastTM

Abrasive Blasting Process

Tank 1: Coal Slag Abrasive
The first tank was blasted using coal slag. The performance and cost-effectiveness of this abrasive were recorded for comparison.

Tank 2: GMA ToughBlast™ Garnet
The second tank, which had a thicker coating than the first, was blasted using GMA ToughBlast™ Garnet, recommended by BlastOne International, a GMA distributor partner. Two high-production MegaBlasters, each equipped with a 1,600-cfm compressor, were utilized for the task.

Table 2 (797 x 437 px)-3

“My working day is shorter as I don’t have to stop and wait for the dust to settle to see what we are doing. The visibility during the blasting session with GMA ToughBlast™ was excellent, significantly improving our efficiency.”
Project Foreman

Using GMA ToughBlast™

The foreman reported outstanding visibility during the blasting session with GMA ToughBlast™, a significant improvement over the coal slag used on the first tank. The enhanced visibility reduced downtime, as there was no need to wait for dust to settle, making the workday more efficient.

Productivity

37.7% or 72.5 ft²

Per hour more efficient

placeholder-icon-white-bg
Consumption

42% or 160 tonnes

less abrasive

Labour

22.9 days or 60%

Less labour

Key Project Outcomes

  • Overall time savings: 60% time saving, reduced from 43 days to 27 days.
    Cost Savings: The use of GMA ToughBlast™ garnet resulted in a 7.7% reduction in total project costs.
  • Performance: The GMA ToughBlast™ provided superior performance, particularly noted in the blasting of the thicker coatings on the second tank. 
  • Efficiency: Improved visibility and reduced dust levels led to a shorter workday and higher overall productivity.

Summary

This case study highlights the advantages of using GMA ToughBlast™ garnet over traditional coal slag in large-scale maintenance projects. The superior performance, combined with significant cost savings and improved working conditions, demonstrates why GMA ToughBlast™ is a preferred choice for abrasive blasting in industrial maintenance.

Learn more about GMA ToughBlast™